Barzaga v CA Digest

G.R. No. 115129 February 12, 1997 Facts:  The petitioner’s wife was suffering from a debilitating ailment and with forewarning of her impending death, she expressed her wish to be laid to rest before Christmas day to spare her family of the long vigils as it was almost Christmas. After his wife passed away, petitioner bought materials from herein private respondents for the construction of her niche. Private respondents however failed to deliver on agreed time and date despite repeated follow-ups. The niche was completed in the afternoon of the 27th of December, and Barzaga's wife was finally laid to rest. However, it was two-and-a-half (2-1/2) days behind schedule. Issue: Was there delay in the performance of the private respondent's obligation? Ruling: Yes. Since the respondent was negligent and incurred delay in the performance of his contractual obligations, the petitioner is entitled to be indemnified for the damage he suffered as a consequence of the delay...